Is it difficult for you to decide to purchase PMI CAPM exam dumps questions? CertQueen provides FREE online Certified Associate in Project Management (CAPM)® CAPM exam questions below, and you can test your CAPM skills first, and then decide whether to buy the full version or not. We promise you get the following advantages after purchasing our CAPM exam dumps questions.
1.Free update in ONE year from the date of your purchase.
2.Full payment fee refund if you fail CAPM exam with the dumps

 

 Full CAPM Exam Dump Here

Latest CAPM Exam Dumps Questions

The dumps for CAPM exam was last updated on Jul 15,2025 .

Viewing page 1 out of 49 pages.

Viewing questions 1 out of 248 questions

Question#1

In an organization with a projectized organizational structure, who controls the project budget?

A. Functional manager
B. Project manager
C. Program manager
D. Project management office

Question#2

Why is tailoring required in a project?

A. Because a one-size-fits-all approach avoids complications and saves time.
B. Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required.
C. Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project.
D. Project managers should apply every process in the PMBOK Guide to the project, so tailoring is not required.

Question#3

Which of the following can be used as an input for Define Scope?

A. Product analysis
B. Project charter
C. Scope baseline
D. Project scope statement

Question#4

When would resource leveling be applied to a schedule model?

A. Before constraints have been identified
B. Before it has been analyzed by the critical path method
C. After it has been analyzed by the critical path method
D. After critical activities have been removed from the critical path

Question#5

A project manager needs to request outside support......manager need to create. A project manager needs to request outside support for a statement ot work (SOW) that is not precise.
Which kind of contract does the project manager need to create?

A. Time and material (T&M)
B. Cost plus fixed fee (CPFF)
C. Fixed price
D. Cost plus award fee (CPAF)