C_TS412_2021

Practice C_TS412_2021 Exam

Is it difficult for you to decide to purchase SAP C_TS412_2021 exam dumps questions? CertQueen provides FREE online SAP Certified Associate - SAP S/4HANA Project Systems C_TS412_2021 exam questions below, and you can test your C_TS412_2021 skills first, and then decide whether to buy the full version or not. We promise you get the following advantages after purchasing our C_TS412_2021 exam dumps questions.
1.Free update in ONE year from the date of your purchase.
2.Full payment fee refund if you fail C_TS412_2021 exam with the dumps

 

 Full C_TS412_2021 Exam Dump Here

Latest C_TS412_2021 Exam Dumps Questions

The dumps for C_TS412_2021 exam was last updated on Aug 19,2025 .

Viewing page 1 out of 4 pages.

Viewing questions 1 out of 23 questions

Question#1

You have activated the workflow for confirmation variances in SAP Project System.
Who is the receiver of this workflow item?

A. The person responsible for the work center
B. The person responsible for the superior WBS element
C. The MRP controller for the network
D. The person responsible for the network activity

Question#2

In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity.
How does the system support this scenario?

A. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)
B. The purchase order is updated automatically to match the new quantity while saving the project.
C. A workflow can be triggered to inform the purchasing group.
D. The system automatically creates a new purchase requisition with the difference to the original quantity

Question#3

Cost & Budget
You are using network and internal activities in your project. You have already create a purchase requisition and the bid invitation.,
and have entered the quotation ...
What is the typical sequence for the following business transactions and document.

A. Benefic check - Acceptance of performed service- vendor selection - purchase order handing- purchase order monitoring-Good receipt - invoce ..
B. Vendor selection - purchase order handing- purchase order monitoring- Benefic Check-Acceptance of performed services.
C. Vendor selection - purchase order handing - invoice receipt - purchase order monitoring -Good receipt.
D. Vendor selection- Purchase order handing-purchase order monitoring-Good receipt-Invoice receipt.

Question#4

Resources
How are capacity requirements determined?

A. Independent of scheduling and according to the capacity planner group.
B. Using scheduling and the capacity category.
C. Using the control key of an activity.
D. Using scheduling and distribution key.

Question#5

Where do you maintain the length of the project ID?

A. Special characters
B. Project coding mask
C. Project profile
D. Project type