Is it difficult for you to decide to purchase CIPS L6M5 exam dumps questions? CertQueen provides FREE online Strategic Programme Leadership L6M5 exam questions below, and you can test your L6M5 skills first, and then decide whether to buy the full version or not. We promise you get the following advantages after purchasing our L6M5 exam dumps questions.
1.Free update in ONE year from the date of your purchase.
2.Full payment fee refund if you fail L6M5 exam with the dumps

 

 Full L6M5 Exam Dump Here

Latest L6M5 Exam Dumps Questions

The dumps for L6M5 exam was last updated on Jun 15,2025 .

Viewing page 1 out of 1 pages.

Viewing questions 1 out of 6 questions

Question#1

When is the best time to define acceptance criteria for a project?
Answer Options:

A. Upon completion
B. During each milestone
C. When writing the Project Initiation Document
D. As part of the Project Audit

Explanation:
Acceptance Criteria should be set before the project starts in the Project Initiation Document (PID) (p.137).
Option A is too late, as the project is already completed.
Option B is iterative, but criteria should be predefined.
Option D is for evaluation, not definition. [P.137]

Question#2

Dave, Head of HR, is introducing the "Person-Organization Fit" model.
Q: What will this help achieve? Answer Options:

A. Ensuring staff meet their KPIs
B. More successful recruitment
C. Less discrimination in the workplace
D. Better relationships with suppliers

Explanation:
The Person-Organization Fit model helps in hiring employees whose values align with the organization (p.194).
Option A relates to performance management, not hiring.
Option C addresses diversity policies, not cultural fit.
Option D focuses on supplier relations, not internal recruitment. [P.194]

Question#3

Which of the following statements about investment appraisal techniques are true? (Select all that apply.)
Answer Options:

A. Non-discounted cash flow methods focus on profit maximization
B. Return on Capital Employed (ROCE) is expressed as a percentage of the value of assets used to generate profit
C. Payback analysis ignores cash flow after the business recovers its costs
D. Internal Rate of Return (IRR) can be used with Net Present Value (NPV)

Explanation:
Option B is correct C ROCE is expressed as a percentage (p.87).
Option C is correct C Payback Analysis only considers the break-even point (p.83).
Option D is correct C IRR and NPV are often used together (p.82).
Option A is incorrect C Profit maximization is not the primary focus of non-discounted cash flow methods. [P.82-87]

Question#4

Jennifer is drafting a contract with a "termination for convenience" clause. Q: What obligations should be included in this clause? (Select all that apply.)

A. The return of any advance payments
B. The destruction of confidential information
C. The smooth transition of services to a new supplier

Explanation:
A termination for convenience clause outlines the responsibilities when a contract is ended early by mutual agreement (p.135).
Returning advance payments ensures fairness.
Destroying confidential data prevents misuse.
Smooth service transition minimizes disruptions.
A review meeting is not mandatory, so it is incorrect. [P.135]

Question#5

1.Which of the following is true about Engineering, Procurement, and Construction (EPC) Contracts? (Select all that apply.)
EPC contracts, commonly referred to as Turnkey Projects, are widely used in construction and infrastructure projects. These contracts require the contractor to design, procure materials, and construct the project to deliver a complete and operational facility to the client. Answer Options:

A. The contractor is responsible for the design aspect of the construction
B. The contractor may operate the building for a certain period after completion
C. These contracts are commonly known as Turnkey Projects
D. These contracts are sometimes referred to as Design and Build Contracts
E. These contracts are used when forming a partnership between a private and public organization

Explanation:
The correct answers are 1, 3, and 4 (p.8). Option 2 is incorrect as it describes a DBO (Design-Build-Operate) contract rather than an EPC contract. Option 5 is incorrect because it describes a PPP (Public-Private Partnership) contract, not an EPC contract. [P.8]